Termination Gone Wrong: A $697,805 Mistake

Termination Gone Wrong: A $697,805 Mistake

Hale Corp Pty Ltd v Ng [2026] VSC 492

 

FACTS

In December 2019 Cheng Lam Ng and Ai Hiang Tan (the Owners) engaged Hale Corp Pty Ltd (Hale) to build a house in Bulla, Victoria. This was a substantial building contract, initially priced at $6,553,759 and with subsequent agreed variations increasing that by a further $1,154,691. The works commenced, but the parties fell into dispute. In April 2021 the Owners issued a notice to show cause alleging multiple substantial breaches, including:

 

  • Failure to provide security guarantees;
  • Failure to provide a program;
  • Failure to supervise necessary work;
  • Failure to bring the works to completion by the date for completion;
  • Defects in the works; and
  • Failure or refusal to cooperate.

 

Then, being unsatisfied with Hale’s response, the Owners sent a termination notice. Hale considered the notice to be a repudiation, which it accepted and then it terminated the contract. Hale issued proceedings in VCAT and those proceedings were transferred to the Supreme Court.

 

ISSUE

Did the owners properly terminate the contract or was their attempt to do so a repudiation?

 

FINDING…

…